concrete slab drying time
07-07-2009, 02:21 PM
Post: #1
concrete slab drying time
I've got a deck that I've got to measure, and I hear that they dry differently, or that ASTM classifies them differently, or something along those lines, because it's up off the ground. Is that true?
Find all posts by this user
Quote this message in a reply
07-09-2009, 01:46 PM
Post: #2
RE: concrete slab drying time
Is your concrete slab on a metal deck? How did you pour it?

Basically, ASTM F2170 says that if the slab is drying only from the top, you should drill to 40% into it for your test. If it's drying from both sides (which means it's not on a metal deck or sitting on the ground with a vapor retarder below) than you only should drill down 20% of the thickness
Visit this user's website Find all posts by this user
Quote this message in a reply